You are here: Home > Steel News > Latest Steel News > Bolivia’s...

Bolivia’s ESM resumes construction works following 15-month delay

Tuesday, 22 June 2021 21:22:19 (GMT+3)   |   Sao Paulo
       

The Bolivian ministry of mining has resumed construction works at its Empresa Siderúrgica Mutún (ESM) iron ore and steelmaking complex. Works were first expected to resume in March this year, as reported by SteelOrbis.

The minister of mining, Ramiro Villavicencio Niño de Guzmán, blamed the former president for the 15-month delay. Guzmán said construction works should now finish in 2023, with the plant’s start-up expected to late-2023.

Earlier this year, the Bolivian government said construction works could be completed by late 2022. Construction works were first expected to begin in 2017 but were then postponed for June 2018.

Sinosteel commenced preliminary works in the area in July 2018. The complex should have a 650,000 mt/year capacity iron ore concentration plant, out of which it will produce 400,000 mt/year of pellets and 250,000 mt/year of sponge iron.


Similar articles

Indian integrated steelmaker Shri Bajrang to raise $30 million to fund brownfield expansion

26 Nov | Steel News

Bolivia’s ESM to resume construction works by March

23 Feb | Steel News

Equipment tests started at Bolivia’s El Mutún steel complex

05 Nov | Steel News

Bolivia’s El Mutun iron ore and steel complex will start operations in September

20 Aug | Steel News

Bolivia’s El Mutun project to start finished steel production in March 2025

27 May | Steel News

Bolivia’s El Mutun considering cooperation with Brazilian pig iron producer

08 May | Steel News

Bolivia reports advance of El Mutun steel complex

06 Mar | Steel News

Bolivia updates status of El Mutun steel complex

15 Jan | Steel News

Iron ore exports declined in 2023 at Bolivia’s El Mutun

02 Jan | Steel News

Peru’s Aceros Arequipa commissions new pipe plant in Bolivia

24 Nov | Steel News