You are here: Home > Steel News > Latest Steel News > ArcelorMittal...

ArcelorMittal to double production at Sestao plant

Thursday, 29 December 2016 16:54:41 (GMT+3)   |   Shanghai
       
Global steel giant ArcelorMittal has decided to double its hot rolled coil production at its Sestao plant in northern Spain, as reported by media sources.
 
Accordingly, the company will increase its production from the current 15,000 mt per month to 30,000 mt per month in the first quarter of 2017.
 
ArcelorMittal had decided to idle its Sestao plant in January this year, due to extremely adverse market conditions. The plant was reopened in September. 

Similar articles

ArcelorMittal Asturias starts production at revamped slab caster No. 1 in Avilés

22 Mar | Steel News

ArcelorMittal to idle another two BFs in Europe over summer

19 Jun | Steel News

ArcelorMittal to stop Gijon blast furnace B in July for 40-45 days

17 May | Steel News

ArcelorMittal halts production at color coating line in Spain

14 Feb | Steel News

ArcelorMittal to restart tinplate production in Spain’s Basque region

20 Jan | Steel News

ArcelorMittal halts Brazilian rolling mill expansion

01 Nov | Steel News

ArcelorMittal TB Zaragoza to provide tailored blanks for Opel Meriva

18 Feb | Steel News

ArcelorMittal Asturias starts production at revamped slab caster No. 1 in Avilés

22 Mar | Steel News

ArcelorMittal to idle another two BFs in Europe over summer

19 Jun | Steel News

ArcelorMittal to stop Gijon blast furnace B in July for 40-45 days

17 May | Steel News